  • Fervo Energy aims to have 100 MW online by New Year and half a gigawatt by 2028
  • Fervo Energy, an enhanced geothermal systems (EGS) provider backed by the Chocolate Factory, achieved first power at its Cape Station power plant in Beaver County, Utah this week.
  • Back in 2023, Fervo demonstrated the tech at its Project Red site, which was capable of generating a modest 3.5 MW of power.
  • While the plan is expected to produce just 100 MW of capacity by January 1, its capacity is expected to swell to half a gigawatt by 2028.
  • In addition to its deal with Fervo, Google has also agreed to buy power from Ormat Technologies’ competing geothermal operations.

5 sentences from our version of the report, chosen to cover it. Nothing here is written; every line is in the article below. How

Headline check

All three things this headline claims are in the report.

Figures, names and quoted words in the headline, looked for in the report itself — not in the summary above. How this is checked

Read the full reportHide the full report2 min

Fervo Energy aims to have 100 MW online by New Year and half a gigawatt by 2028

Google's bet on geothermal energy is starting to pay off. Fervo Energy, an enhanced geothermal systems (EGS) provider backed by the Chocolate Factory, achieved first power at its Cape Station power plant in Beaver County, Utah this week.

The first of three 33 MW GeoBlocks has begun supplying electricity to the grid and is expected to reach commercial operation next week, with another 66 MW of capacity expected to come online by New Year. Fervo says the station has the potential to eventually scale to more than four gigawatts of capacity.

For now, the company is working toward fulfilling 900 MW of contracted capacity.

The deployment builds on years of research and development into EGS technologies that use heat generated by the Earth's crust to convert water into steam, which, like in most other power plants, is converted into energy using turbines.

The trick is getting the water deep enough in the first place. To overcome this challenge, Fervo borrowed technologies originally developed by the oil and gas industry.

Two parallel wells are dug to around 8,000 feet (2,438 meters) below the surface. The rock is then fractured to allow water to pass between the two, heating the water to 190 degrees Celsius in the process.

Back in 2023, Fervo demonstrated the tech at its Project Red site, which was capable of generating a modest 3.5 MW of power. Fervo’s Cape Station is orders of magnitude larger in scope.

While the plan is expected to produce just 100 MW of capacity by January 1, its capacity is expected to swell to half a gigawatt by 2028.

One of the beneficiaries of the buildout is Google. The search and advertising giant has been an early proponent of geothermal power generation going back to at least 2008.

In addition to its deal with Fervo, Google has also agreed to buy power from Ormat Technologies’ competing geothermal operations. Earlier this year, the Chocolate Factory announced a 150 MW deal with Ormat and Nevada’s NV Energy to fuel its datacenter expansion.

Faced with grid constraints, Meta has been investing in the tech. Back in 2024, the company partnered with Sage Geosystems to deliver up to 150 MW of power.

However, compared to conventional energy generation, geothermal still faces challenges as noted by think tank Rhodium last year. While the firm estimates the tech could meet up to 64 percent of datacenter demand by the end of the decade, those bit barns could end up paying a 20 percent premium for it. ®

You are reading our version, not theirs. This is The Register's report with its verdicts and loaded words taken out. Plain description stays, and so do adjectives that carry a fact, such as "former" or "federal". The reporting, the facts and the quotations are theirs — quotations are never edited — and the indicators beside it measure this version. Hover or tap Adjectives to see every one left in the text.

How this outlet filed it, and how we rewrote it

No other newsroom we read has filed on this event, so there is nothing to compare it with yet.

Outlet Niral ScoreAdjectivesSourcingHappiness
The Registeras they published this story 11.3 7 17 50
Mundane Readneutralized from The Register 10.5 6 17 50

Sign in to react.

Comments

Nothing here yet.

Sign in to comment.

Questions

Readers can ask a question about this story here. Questions and answers are for subscribers. Sign in to read them.

Comments are read before they appear where anything in them needs a person to look. Nothing posted here is ever deleted; a comment taken down keeps its text and the reason, so the decision can be looked at again. How this works