  • Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.
  • Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources.
  • The notice also comes as AI data center construction faces scrutiny nationally, and as developers take on costs to build capacity for customers like OpenAI.
  • Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that “this notice does not change the financial commitments to this multi-year project.”
  • Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term.

5 sentences from our version of the report, chosen to cover it. Nothing here is written; every line is in the article below. How

An Energy Transfer pipeline intended to deliver gas to the site has also been delayed nearly six months, to Feb. 1, 2027.

Headline check

The one thing this headline claims is in the report.

Figures, names and quoted words in the headline, looked for in the report itself — not in the summary above. One claim in this headline could be checked, so this is a narrow pass and not a thorough one. How this is checked

Read the full reportHide the full report2 min

Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.

Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2028 target to come online.

The notice also comes as AI data center construction faces scrutiny nationally, and as developers take on costs to build capacity for customers like OpenAI.

Oracle maintains that it does not expect a delay. “Project Jupiter remains on our planned schedule,” Oracle said in a statement to CNBC. “We are fully committed to New Mexico and confident in our path forward.”

Blue Owl Capital, whose unit received the notice, said in its own statement to CNBC that “this notice does not change the financial commitments to this multi-year project.”

Neither Oracle nor Blue Owl immediately responded to TechCrunch’s requests for comment.

Still, the notice follows a string of setbacks at the site, many of them tied to its energy supply. The campus, designed to handle 2.45 gigawatts, is meant to run on gas-powered fuel cells from Bloom Energy, which makes a gas supply central to its timeline

An Energy Transfer pipeline intended to deliver gas to the site has also been delayed nearly six months, to Feb. 1, 2027, after regulators repeatedly denied permits for the line. In August, Bloomberg reported that the pipeline’s route had been changed following those rejections. A separate air quality permit for the fuel cell system that would power the campus is also pending. The state’s environment department faces a Nov. 23 deadline to decide.

Project Jupiter is one of the flagship sites of Stargate, the AI infrastructure initiative Oracle, OpenAI and SoftBank announced with President Donald Trump early in his second term. The campus has drawn opposition from residents and environmental groups and has become a political flashpoint ahead of the midterm elections. Oracle has responded with a public outreach campaign in the state aimed at winning over the project’s critics, according to Bloomberg.

Anthropic says its biology lab has already found something big Julie Bort

PitPro’s first tire-changing robot goes live in Canada Sean O'Kane

Anthropic is operating a lab that conducts biology experiments Julie Bort

You are reading our version, not theirs. This is TechCrunch's report with its verdicts and loaded words taken out. Plain description stays, and so do adjectives that carry a fact, such as "former" or "federal". The reporting, the facts and the quotations are theirs — quotations are never edited — and the indicators beside it measure this version. Hover or tap Adjectives to see every one left in the text.

How this outlet filed it, and how we rewrote it

No other newsroom we read has filed on this event, so there is nothing to compare it with yet.

Outlet Niral ScoreAdjectivesSourcingSentimentHappiness
TechCrunchas they published this story 7.2 5 68 -0.1 50.2
Mundane Readneutralized from TechCrunch 4.7 3 68 -0.1 50.2

Sign in to react.

Comments

Nothing here yet.

Sign in to comment.

Questions

Readers can ask a question about this story here. Questions and answers are for subscribers. Sign in to read them.

Comments are read before they appear where anything in them needs a person to look. Nothing posted here is ever deleted; a comment taken down keeps its text and the reason, so the decision can be looked at again. How this works